RR Kabel

Introduction

In our research we found that today every organization is facing problem of sewage and sanitation. And they are using the traditional method for its solution which is less effective and more costly and it has many other hurdles too.

As we have develop an innovative solution (DRAYNZYME) for such problem which is effective, less costly and better in many ways.

To provide this benefit to RR KABEL we have visited the plant on 09-10-2014.

The meeting was done between RR KABEL And AS renewable Energy pvt. ltd. in the presence of Mr.RAKESH PATEL from RR KABEL and and Mr. Sunil Kumar Yadav (Marketing Executive) from A S renewable Energy pvt. ltd.

The conclusion came as to give demo to judge effectiveness of the product.

So according to the detail provided by RR KABEL, we did sample dosing in the canteen chamber.

visit

Visit-1

RR KABEL plant, Problem in Canteen

Visit-1

We visited the RR KABEL plant on 15th October 2014 and found three major problem in canteen

  Appalling & disturbingly foul odour

  Undigested sludge in canteen chamber

  Top layer of sludge was hard

  No water was visible from outside

Visit-1 Our Solution

RR KABEL plant, Solution RR Kabel Plant, Draynzyme & Booster Peck, FOG candle

visit-1 Our Solution

We applied the combined dosing of following on 02-01-2015 Based on Approx Flow was give by APOLLO officials.

  2 DRAYNZYME FOG BUSTERS with BOOSTER PACK

  2 SEWAGE AID

Visit-2

FOG Candle & Booster Pack, Provided RR Kabel

Visit-2

So with the permission of Mr.Rakesh patel sir we arranged two more FOG candle with booster pack and visited the plant again with the purpose of dosing on 03-11-2014.
So with the permission of Mr.Rakesh patel sir we arranged two more FOG candle with booster pack and visited the plant again with the purpose of dosing on 03-11-2014.

Visit-3

Draynzyme & Booster Pack, Visit Rr Kabel

Visit-3

To see the effect of draynzyme & booster peck we visited the plant on 23-02-2015. At the visit both Mr. Luies Coelho (Executive Admn.) admitted that there were no odour & sludge was completely degraded.

Conclusion

We realize the following changes as compare to first visit.

Before dosing of Draynzyme

  •   Appalling & disturbing foul odour
  •   Top Layer of sludge was very hard
  •   Excessive amount of undigested sludge
  •   Due to very hard level of sludge, no amount of water was visible

After dosing of Draynzyme

  •   The foul odour was COMPLETELY REMOVED
  •   The sludge layer become SOFTENED
  •   The Sludge digestion process started
  •   After dosing we can see water level up with degraded sludge